Use two Costpoint screens to enter budget figures into the C/SSR report: Maintain C/SSR Budgets (this screen) or Import CSSR Budgets. Use this screen to enter the budgeted costs of scheduled work and work performed. You can upload your budgets from a file using the Import C/SSR Budgets screen. Information from this screen prints in columns 7.(2) and 7.(3) of the C/SSR.
To ensure correct budget figures, use this screen before creating the C/SSR tables.
Click to select the project for which you are entering budget data.
Click to add data to this table.
Enter, or click to select, the project using the Work Breakdown Structure (WBS) of the project tree.
Enter the fiscal year for this project's row of budgeted data.
Enter the period for this project's row of budgeted data.
Enter the subperiod for this project's row of budgeted data.
Enter the work scheduled amount for this project's row of budgeted data. This amount prints in item 7.(2)a. of the C/SSR.
Enter the work performed amount for this project's row of budgeted data. This amount prints in item 7.(3)a. of the C/SSR.
Enter the Cost of Money (COM) on work scheduled for this project's row of budgeted data. This amount prints in item 7.(2)b. of the C/SSR.
Enter the Cost of Money on work performed for this project's row of budgeted data. This amount prints in item 7.(3)b. of the C/SSR.
Enter the General & Administrative (G&A) costs on work scheduled for this project's row of budgeted data. This amount prints in item 7.(2)c. of the C/SSR.
Enter the General & Administrative costs on work performed for this project's row of budgeted data. This amount prints in item 7.(3)c. of the C/SSR.