Use this screen to enter project deliverables and to track dates for each deliverable. Use it to initially enter all known deliverables for a project. Thereafter, use it to update the due date, date delivered, date accepted, and notes.
This screen is also available as a subtask on the Manage Project User Flow screen: Deliverables.
Enter, or click to select, a valid project for which to enter data. This is a required field. The unlabeled field displays the project description.
This field defaults to the last deliverable number for the project plus one. If no deliverable numbers are found, it defaults to 000. You can enter any deliverable number. This is a required field.
This field displays the amount of the deliverable.
This field displays the description of each deliverable number.
This field displays the code of the customer.
This field displays the purchase order number of the customer.
This field displays the work order number of the customer.
This field displays the original due date of the deliverable that was agreed upon in the contract.
This field displays the revised due date of the deliverable. This is the date that it is currently due and can represent more than one revision. If tracking separate revisions is required, you can assign and track a separate deliverable number for each revised due date.
This field displays the date on which the deliverable was delivered to the customer.
This field displays the date on which the deliverable was invoiced to the customer.
This field displays the date on which the deliverable was accepted by the customer.
This field displays notes entered by the user regarding the deliverable. All notes are stored and are available for reporting purposes.