POOL SETUP TIPS

Although setting up cost pools and service centers is intimidating to most people, it is reasonably straightforward in Costpoint. You set up a cost pool by defining the following:

The standard equation used in the allocation of cost pools is provided as follows, specifying the factors involved in the setup process:

Rate or %             =          Account/Organizations containing COSTs to be allocated

                                         Account/Organizations forming the BASIS (that is, Direct Labor)

The pool is CREDITed for the entire amount of the numerator and the debit (or allocation receipt) is made to the account/orgs specified as the DEBIT ALLOCATION account/orgs.

Employee Benefit Pool Example

Rate or %             =          Account/Organizations which contain Employee Benefit costs

                                         Account/Organizations which contain Direct and Indirect Labor

Because you cannot allocate employee benefits to the direct and indirect labor account/organization combinations directly without distorting the amount of labor dollars in those accounts, you must define a separate set of account/organizations to receive the employee benefit allocation. You can then use these debit allocation accounts in the pool or base of other pools, if it is necessary.

Account

Org

Description

0501

1.1.1

FICA

0502

1.1.1

FUTA

0503

1.1.1

SUTA

0504

1.1.1

Vacation Leave

0505

1.1.1

Sick Leave

0506

1.1.1

Holiday Leave

0507

1.1.1

Pension

0508

1.1.1

Group Insurance

0599

1.1.1

Credit For Empl Ben Pool

 

 

Base Account/Org

Allocation Account/Org

8001/1.1.1 D/L

0590/1.1.1 FRINGE ON D/L

6001/1.1.1 O/H LABOR

0591/1.1.1 FRINGE ON O/H LAB

7001/1.1.1 G/A LABOR

0592/1.1.1 FRINGE ON G/A LAB

Pool Setup Basics

In order to create a cost pool in Costpoint, certain information is required. Combined, this information defines the pool. The pieces include:

The allocation group number defines the pool as one that is used in the allocation of amounts to projects or simply as an "informational" pool used only for providing information to management. Allocation Group 1 is the only group whose pools allocate costs to projects. All other allocation groups (2 and above) are considered informational only — a Statement of Indirect is produced, showing the rate that was calculated, but they are not used to allocate to projects.

Some examples of using allocation groups other than Group 1 include:

The pool number defines which number in the "set" or group of pools that a particular pool is. Pool numbers do not have to be sequential. A valid set of pool numbers could be: 1=Fringe Full Time; 2=Overhead; 3=General & Administrative; and 4=Fringe Part Time. The pool number does not affect the order in which the pools are processed. 

The sequence number defines the order or sequence in which a pool is allocated within the "set" or Group to which it belongs. It is very important to make sure that your pools are processed in the proper order so that accurate rates are produced. You can modify sequence numbers as often as necessary. You can individually modify the sequence number in each pool or use the Manage Pool Processing Sequence Numbers screen. If you modify the sequence numbers of your pools, be sure to execute the Build Rate Application Table screen before you attempt to recompute the indirect rates. Using the previous example of pool numbers, you could use the sequence numbers to make sense of the allocation scheme:

Seq #

Pool #

Name

1

1

Fringe Full Time

1

4

Fringe Part Time

2

2

Overhead

3

3

General & Administrative

 

The fiscal year defines the length of time that a pool is active. If the same pool is active for multiple fiscal years, you must clone it from fiscal year to fiscal year. You can clone pools by using either the Clone feature on the Manage Cost Pools screen or by using the Copy Pools toolkit.

Once the pool is created, by virtue of the fact that it has an allocation group number, pool number, sequence number, and fiscal year, you can specify other key information about it on the main Manage Cost Pools screen. This information includes the long name of the pool (which prints on various project reports such as the Project Status Reports and the Statement of Indirects), a description of its basis (direct labor, total labor, total cost, labor hours, etc.), a basis type (hours, dollars, or units), and three other pieces of information:

In addition, if you plan on using the Create Cost Transfer Journal Entries screen, you must complete the Debit Account and the Credit Account fields in the Financial Statement Reclass Accounts group box on the Manage Cost Pools screen. When the cost of a project is charged to the performing orgs and the revenue is collected by the owning organization, the Cost Transfer Journal entry reallocates the cost from the performing organization to the owning org. You can then print income statements by organization. The direct and indirect costs are reallocated during this process, and the program uses the accounts entered in this screen to reallocate by pool.

After you have provided all of this information for a given pool, you must finish setting up the Cost Account/Organizations, Base Account/Organizations, Allocation Account/Organizations, and Credit Account/Organization. Assign these account/organization combinations in the subtasks on the Manage Cost Pools screen. When you finish, you are ready to process your pools. The remaining part of this topic examines cost accounts, credit accounts, base accounts, and debit allocation accounts.

How to Specify the Pool Cost Accounts

How To Specify the Pool Base and Allocation Accounts

How to Specify the Credit Account

How to Set Up Target and Provisional Rates

How to Set Up Service Centers

Troubleshooting Your Pool Setup