Use this screen to create project budgets; click to select an existing project for the creation of a budget. Click
to retrieve any existing project budget.
Use this screen to get a summary of total project budget amounts. You cannot edit the amounts in this screen; they derive from the detail subtasks accessed by the links at the bottom of the screen.
Use it when creating a project budget or any time you revise either your baseline or workplan budget.
This screen has two tabs:
Total Budget — The fields in this non-editable tab display amounts derived from data entered in the subtasks.
Info — In this tab, you can choose settings that control this screen and its subtasks. When you create a new budget, all other tabs and subtasks on this screen are inoperable until you have selected and saved a labor and unit budgeting method in this tab.
Click to select a project with an existing budget. You can also enter, or click
to select, a new project budget.
This non-editable field displays the name of the selected project.
Enter, or click to select, the revision for this workplan budget. This field is non-editable for baseline budgets, because there can be only one version of a baseline budget. Revisions are created on the Manage Project Budget Revisions screen.
If no revision displays here, select the Allow Workplan Budgets check box on the Configure Project Budget Settings screen to activate the revision function, then create revisions on the Manage Project Budget Revisions screen.
Use the options in this group box to select either the Baseline or Workplan budget.
Select this option to create a baseline budget.
Select this option to create a workplan budget.
Subtask |
Description |
ETC |
Click the ETC link to open the Estimate to Complete subtask, where you can forecast the Estimate To Complete (ETC) amounts for Direct, Subcontractor, Fee, Units, and Labor. |
Indirect |
Click the INDIRECT link to open the Indirect subtask, where you can recalculate your burden or indirect charges by fiscal year and pool for reporting purposes only. The calculation is derived based on the burden template selected on the Info tab. If a burden rate is modified on an individual subtask row, without using a burden template, the amounts from those edited rows are not included. This subtask is not available unless the Enable Indirect Subtask check box is selected in the Configure Project Budget Settings screen. |
Fees |
Click the FEES link to open the Fees subtask and enter fees in place of, or in addition to, using a multiplier for calculating profit. To calculate the profit for the project, use either a fee percentage or a fixed fee amount. You can use the other fee amount in addition to the fee percentage or the fixed fee. Click the Recalculate button after changing any amounts in this subtask. |
Units |
Click the UNITS link to open the Units subtask, where you can enter unit cost or unit price amounts, quantities, categories, and/or multipliers to calculate your unit budget. Click the Recalculate button after modifying any amounts in this subtask. |
Labor |
Click the LABOR link to open the Labor subtask. In this subtask, you can enter labor costs or bill rate, burden rate, labor hours, labor categories, vendor or employee data, and/or multipliers to calculate your labor budget. Click the Recalculate button after changing any amounts in this subtask. |
Direct Subtask Project Budget Detail |
Click the DIRECT link to open the Direct subtask. In this subtask, you can enter direct costs, burden rate, vendor data, and/or multipliers to calculate your direct cost budgets. Click the Recalculate button after changing any amounts in this subtask. |