Use this screen to enter project budgets by fiscal period for direct accounts, indirect pools and fees. For each fiscal year, you can track multiple budget revisions. You can enter a default fee rate to be applied to each cost element on the Manage Project Total Budget screen. If you don't want to manually enter indirect expenses budgets by pool, you can leave the Budget % and Amount blank (in the Indirect subtask) and let Costpoint update the indirect cost budgets for you. You can do this using the Apply Indirect Costs to Budgets screen.
Enter data in this subtask after you have initialized the project and set up budget revisions. Remember to save this screen each time you use the Spread, Fill, Move, or Escalate subtasks. Existing budget information can be lost if you do not save before adding new rows (accounts) to the Table Window.
Enter a valid project, or click to select one. The description of the project automatically displays next to the project.
Enter, or click to select, a valid revision number for this project and fiscal year.
Enter a valid organization number or click to select one. The description of the organization displays next to the organization number.
Use this drop-down list to select a valid fiscal year.
Enter an account or click to select a valid account for this project and organization.
Enter, or click to select, a valid period for the fiscal year.
Enter, or click to select, a valid subperiod for the fiscal year and period.
Enter a budgeted amount for this direct account.
Enter the fee percent for this direct account or accept the default from the Total Budget subtask. Costpoint uses this percent to calculate Fee Amt.
Enter a fee amount for this direct account or accept the calculated amount. If you modify the amount, Costpoint recalculates the Fee %.
This field is non-editable. The indirect costs on the Indirect subtask are accumulated for this account and displayed.
This field displays the total fee on indirect costs associated for this account.
This field displays the total fee accumulated from direct and indirect fee for this account.
This field displays the total budgeted amount including fee for this account.
This non-editable field displays Costpoint-defined function code assigned to the selected account. Function codes are established on the Manage Project Account Groups screen.
This column displays the name for the selected account.
Subtask |
Description |
Indirect |
Click this link to open the Indirect subtask, where you can enter indirect pool budgets amounts. Use this link after highlighting a row on the main screen. |
Total Budget |
Click this link to open the Total Budget subtask. In this subtask you can view the total direct, indirect, fee percent, fee amount, other fee percent, other fee amount, and cost of money entered for this project, organization, fiscal year, and revision. |
Adjust Actuals |
Click this link to open the Adjust Actuals subtask, where you can adjust period budgeted amounts to the actual amounts incurred, or create a budget based on actual cost data. You can also spread variance amounts between budgeted and actual costs across selected periods within the same fiscal year. |
Spread |
Click this link to open the Spread subtask, where you can spread cost and/or fee amounts across designated periods. Please remember to click |
Fill |
Click this link to open the Fill subtask, where you can automatically fill selected subperiods with specified budgeted amounts. Please click |
Move |
Click this link to open the Move subtask, where you can move a specified budgeted value from one range of periods to another range of periods. Please click |
Escalate |
Click this link to open the Escalate subtask, where you can escalate budgeted amounts by a specified escalation factor. Please click |