Use this non-editable subtask to view the organization detail for a given row. This subtask displays the same data as the main screen but provides a row for each performing organization.
This subtask displays data updated by the Compute Estimate to Complete screen.
This field displays the project ID from the main screen.
This field displays the project description.
This field displays the owning organization from the main screen.
This field displays the owning organization description.
This field displays the name of the project manager from the main screen.
Use this group box to assess the age of the data in the inquiry.
The date on which the Update Incurred Cost for ETC process was last executed is displayed.
The date on which the Compute Estimate to Complete process was last executed is displayed.
This field displays the fiscal year for which information was updated.
This field displays the period for which information was updated.
This field displays the subperiod for which information was updated.
The rate type, actual or target, that was used on the Update Incurred Cost for ETC process is displayed.
This field displays the contract value from the Manage Modifications screen.
This field displays the organization number for the selected project.
This field displays the total cost-incurred amount for the selected project.
This field displays the total estimate-to-complete amount for the selected project.
This field displays the total LREAC amount for the selected project.
This field displays the base budget amount for the selected project.
This field displays the variance amount, which is calculated by subtracting the LREAC from the Base Budget for the selected project.
This field displays the percentage of the project that has been completed.
This column displays the total commitments for the project. The commitments are all the open purchase orders for the project.
This column displays the percent complete calculated with commitments.
Subtask |
Description |
Org Cost Info |
Click this link to view additional cost information about the organization on the row that is highlighted. Information on Incurred costs, Estimate-To-Complete, LREAC, and Base Budget is summarized by type (labor, non-labor, burden, fee, and so on). This subtask is identical to the Cost Info subtask accessed from the main screen. |
Org Cost Detail |
Click this link to view cost detail for a given organization. It displays the same information as the main screen but provides a row for each cost element. This subtask is identical to the Project Cost Detail subtask accessed from the main screen. |