Use this screen to create the report table from which the C/SSR prints. You must execute this process for the projects and subperiods for which you want a C/SSR. You can select only those projects that have been entered on the Manage CSSR Information screen; however, Costpoint inserts a row for each branch of the project tree selected into the RPT_CSSR_LN table. You can then specify the number of levels that you want to print on the report on the Print Cost Schedule Status Report screen.
Create report tables after entering all budget information on the Manage CSSR Budgets screen or uploading it with the Import CSSR Budgets screen. To ensure the most current data, run this function after you have executed the Compute Burden Costs screen.
Use the fields in this block to create a new parameter ID or to retrieve a previously saved parameter ID. A parameter ID represents a set of screen selection parameters. After you have saved a parameter ID and its related parameters, you can retrieve them using Query.
You can use the retrieved parameters to produce reports and run processes more efficiently and with greater consistency. The saved parameters are also useful and necessary when you want to run the process as part of a batch job. Many users save a unique set of parameters for each different way they run a report or process. When you select a previously saved parameter ID or parameter description, the associated saved screen selection parameters automatically display as selection defaults. The page setup and print options are also included in the saved parameter ID if there are any. You can change any of the associated selection defaults as necessary.
Enter, or click to select, a parameter
ID of up to 15 alphanumeric characters. Choose characters for your parameter
ID that help identify the type of selections you made in the screen, such
as PERIOD or QUARTERLY.
When you save your record, all the selections made in the screen are stored with the parameter ID. Later, you can retrieve the parameter using Query.
You can use the parameter to run the process more efficiently because you can select the parameter ID with its previously defined screen selections. After the default selections display in the screen, you can override the defaults.
Enter, or click to select, a parameter
description of up to 30 alphanumeric characters.
Use the fields in this group box to limit which projects have tables created for them.
Use this drop-down list to select the range of projects to be included in the C/SSR reports. Each project tree is presented on a separate report. Valid options are:
All
One
Range
From Beginning
To End
The default for this field is All.
Enter, or click to select, the first project of the range to include in the C/SSR reports. If you select All or From Beginning in the Options field, this field is inactive. Only projects that were entered on the Manage CSSR Information screen are available for
.
Enter, or click to select, the last project of the range to be included in the C/SSR reports. If you select All, One, or To End in the Options field, this field is inactive. Only projects that were entered on the Manage CSSR Information screen are available for
.
The C/SSR is a cumulative report; use this group box to select project data for all subperiods up to and including the subperiod selected.
This field always displays One.
Enter, or click to select, the last fiscal year to be included in the calculation of the report table.
Enter, or click to select, the last period to be included in the calculation of the report table.
Enter, or click to select, the last subperiod to be included in the calculation of the report table.
This non-editable field displays the ending date of the selected subperiod.
Select this option to use target rates on the report. The target rates are found on the Pool Rates subtask of the Manage Cost Pools screen.
Select this option to use actual rates on the report. The actual rates are found on the Pool Rates subtask of the Manage Cost Pools screen.
Use this group box to include Project Period Budgets in the work-scheduled or work-performed areas of the C/SSR Budgets.
Use this group box to use the Manage Project Budgets by Period screen as the data source for the work-scheduled area of the C/SSR Budget.
Select this check box if work-scheduled data for the selected projects comes from the period budgets created on the Manage Project Budgets by Period screen. If you do not select this check box, the work-scheduled data comes from the Manage CSSR Budgets screen.
Use the drop-down list to select the budget revision to use in the creation of this report table. This field is active after you select the Use Period Budgets check box in this group box.
Use this group box to use the Manage Project Budgets by Period screen as the data source for the work-performed area of the C/SSR Budget.
Select this check box if work-performed data for the selected projects comes from the period budgets created on the Manage Project Budgets by Period screen. If you do not select this check box, the work-performed data comes from the Manage CSSR Budgets screen.
Use the drop-down list to choose the budget revision to use in the creation of this report table. This field is active after you select the Use Period Budgets check box in this group box.